Baldwin Borough News Flash

Posted on: August 11, 2017

2017 Road Repaving

Paving

  • Colewood -- Concrete curbs removed; milled; binder placed.  Inlet work over next two weeks then wearing placement to follow.
  • Ranchview -- Concrete curbs removed; milled; binder placed.  Inlet work and storm install over next two weeks then wearing placement to follow.
  • Overland Trail -- Concrete curbs removed; milled; binder placed.  Inlet work over next two weeks then wearing placement to follow.
  • Blossom -- Concrete curbs removed; milled; binder placed only from Gardenville to Clelia.  Clelia to McAnnulty will be next week with the binder.  Inlet work over next two weeks then wearing placement to follow.
  • Elmwood -- Curb removal is on going.
  • 8/14 week schedule -- Mill Curry, Hollowhaven and Short then binder those roads by weeks end.